Erected and dismantled perimeter scaffold to a bank building to facilitate roofing works. The scaffold stood approximately 7m high with a working deck set 1m below roof height, providing fall protection for the roofing crew throughout the project.
Stair access was incorporated into the design for safe entry and exit to the scaffold. Given the main street location, the build required pedestrian access to be maintained for the duration of works, with the scaffold footprint managed to minimise impact on foot traffic.
Full multi-storey scaffold installation for a six-level commercial tower in central Albury.
Erected scaffold to the front of the Vic Hotel in Rutherglen’s main street to facilitate full renovations and repair works.
Erected and dismantled perimeter scaffold to a church building to facilitate repair works and a full re-roof.